Quick answer: Most bathroom renovations we do in Chatham take 1 to 4 weeks on site, once all materials have arrived. A straightforward tub, vanity and toilet replacement with new flooring can be done in about a week. A full renovation with a tiled shower, moved plumbing or custom work usually takes 2 to 4 weeks, sometimes more. Before work starts, allow 1 to 6 weeks for ordering the vanity, shower door or shower insert, depending on what you choose. Our last four bathrooms in Chatham took between 7 and 21 days on site.
I'm Adam Parker, owner of Urban Structures Construction. Homeowners usually ask "how much?" first and "how long will we be without a bathroom?" right after. Here's the honest answer: what happens each week, which steps can't be rushed, and what causes delays.
Bathroom renovation timelines at a glance
Type of renovation
What's included
Typical time on site
Refresh / replacement
New tub with tiled surround, vanity, toilet, flooring, trim and paint. Fixtures stay where they are.
About 1 week
Full renovation
Gut to the studs, new tub or shower, waterproofing, tile walls and floor, vanity, toilet, fan, lighting, plumbing updates.
2 to 3 weeks
Layout change or custom shower
Everything above, plus moving drains or plumbing, custom shower bases and walls, tight spaces or wall changes.
3 to 4+ weeks
These times assume materials are on site before we start. Waiting on a vanity, shower, glass, or shower doors is the most common reason a bathroom takes longer than it should.
Before week 1: planning and ordering (1 to 6 weeks)
This part happens before anyone swings a hammer, and it's what keeps the on-site time short.
-
Consultation and site visit. We measure, check the floor and ventilation, and talk through how you use the room.
-
Detailed estimate and scope. You get a written scope so everyone knows exactly what's included.
-
Selections. Tile, vanity, toilet, tub or shower base, fixtures, fan, lighting and glass.
-
Order everything. We don't start demolition until the major items are on site or confirmed for delivery. Right now, vanities, shower doors and shower inserts take anywhere from 1 to 6 weeks to arrive, depending on what you choose. Stock items come quickly; custom or specialty pieces take longest.
-
Permit, if needed. In Ontario, adding new plumbing fixtures or moving existing ones generally needs a building permit. Replacing fixtures in the same location usually doesn't. We confirm with the Municipality of Chatham-Kent's Building Services and handle or help with the application.
Week 1: demolition and rough-in
-
Protection. We cover floors and hallways and set up dust control.
-
Demolition. Tile, tub, vanity and drywall come out. This usually takes 1 to 2 days.
-
Check what's underneath. This is when we find out if the subfloor, framing or old plumbing needs repair. In older Chatham-Kent homes, water damage around the toilet and tub is common.
-
Repairs and framing. We fix the subfloor and framing, and build any new walls, niches or benches.
-
Plumbing and electrical rough-in. New drain and supply lines, shower valve, wiring for lighting, outlets and the exhaust fan, which must vent outside, not into the attic.
-
Inspection (if there's a permit) before the walls close.
Week 2: walls and waterproofing
-
Insulation and backer board on the shower walls, and drywall everywhere else.
-
Waterproofing. This is the most important step in the whole job. Shower walls and floors get a waterproof membrane, and each coat needs time to cure. We use the Schluter Kerdi waterproofing system on our tiled showers and tub surrounds: a membrane system that keeps water out of the walls and floor entirely, with matching drains, corners and niches built to work together.
-
Tile starts on the shower walls once the waterproofing is ready.
This is the week people wonder why things seem slow. The answer is cure time. Membrane, thinset and grout all need time to set. Rushing them is how leaks start, and a leak behind tile means tearing it all out again.
Week 3: tile, grout and paint
-
Shower and floor tile. Tile is usually the longest single step. A simple subway pattern goes faster than large-format tile, mosaics or herringbone.
-
Grout and sealing, after the thinset has cured.
-
Paint on walls and ceiling, using a bathroom-rated finish.
Week 4: fixtures and finishing
-
Vanity, toilet, faucet and shower trim are installed.
-
Lighting, fan and mirror go in.
-
Shower glass. Custom glass is usually measured after tile is finished and can take several weeks to arrive. It's one of the items most likely to stretch your timeline, so we measure as early as possible, or use a standard-size door when timing matters.
-
Trim, caulking and accessories like towel bars, grab bars and paper holders.
-
Final inspection (if permitted) and walkthrough with you.
What causes delays (and how we avoid them)
Delay
How we prevent it
Materials not on site
We order everything before demo and confirm delivery dates.
Hidden damage (rot, mould, old plumbing)
We build time and budget contingency in, and show you what we find before we fix it.
Custom glass lead time
We measure as soon as tile is done, or use a standard-size door when timing matters.
Inspection scheduling
We book inspections ahead and plan other work around them.
Changes mid-project
Last-minute changes to tile or layout reset parts of the schedule. We lock selections before we start.
Living without your bathroom
-
If it's your only bathroom, tell us. We can leave the toilet in place for as long as possible, or reinstall it temporarily when needed, so you're never without one overnight.
-
Line up a gym membership, family or neighbours for showers.
-
Schedule it around holidays or guests, not right before them.
Accessible and aging-in-place bathrooms
Curbless showers, grab-bar blocking, wider doorways and comfort-height toilets add some time, mostly in framing and floor work, but they're far easier to do during a renovation than afterward. Urban Structures is certified through the CHBA's Adaptiv Home Renovation program for accessibility work. Learn more about our adaptive home renovations.
Four Chatham bathrooms, four timelines
Every bathroom is different. Here are four recent jobs, all in Chatham. They took between 7 and 21 days on site, and every one had plumbing updates and new trim and paint. One had a surprise: a window hidden behind the wall, which we found once it was opened up (more on that in job 4).
1. Custom cultured marble shower with a “floating” red oak door
About 3 weeks on site
This one called for custom work. We ordered a custom shower base with cultured marble walls and ran new plumbing under the floor. The base has two drains: a trough drain near the low-clearance threshold to keep water from reaching the bathroom floor, and a main drain in the shower itself. To finish it, we built a red oak door and mounted it with hidden fasteners, so it looks like it's floating. Custom work like this takes longer to make and install, which is why it sits at the top of the range.
2. Tiled shower in a tight space with a bulkhead
7 days on site
This one was all about fitting things in. The room was small, a bulkhead ran overhead, and it still needed a full shower, a vanity and a toilet. We waterproofed the shower with Schluter Kerdi, then tiled it with marble-look tile, a built-in niche and a hex mosaic floor. Working around a bulkhead adds careful planning and cutting time, but the result looks like it was always meant to be there.
3. Shower insert, with the drain moved in a concrete floor
About 2 weeks on site
The homeowner knew exactly what they wanted: a shower insert with no seat that fit the space. Finding that insert took some searching, and making it fit meant cutting into the concrete floor to move the drain. We also tiled the floor and added new lighting and an exhaust fan. Moving a drain in concrete adds days for cutting, plumbing, patching and curing before the floor can be finished.
4. A straightforward update, with a hidden window
About 8 Days on site
The fastest kind of job: remove and replace the tub, tile around it over the Schluter Kerdi waterproofing system, swap the old vanity for a floating vanity, replace the toilet with a comfort-height model, and lay new LVT flooring. No layout changes means no waiting on inspections between steps.
The surprise came at demolition: a window that had been covered over behind the wall. Instead of closing it up again, we kept it and worked it into the new tiled tub surround. The bathroom got natural light back, and the plan barely changed. This is why we always plan to adapt once walls are open.
The takeaway: the timeline depends less on the size of the bathroom than on what’s involved. Moving drains, custom pieces and tight spaces add days. A same-layout update can be done in about a week.
See more finished bathrooms in our project gallery.
Frequently asked questions
Planning a bathroom renovation?
We’ll come out, measure and give you a clear written estimate and timeline. Learn more about our bathroom renovations in Chatham-Kent, or Request your free estimate.
About the author
Adam Parker is the owner of Urban Structures Construction Inc. in Chatham-Kent, Ontario. He has more than 22 years of experience in residential construction and renovation, is a licensed G2 gas fitter, and is certified through the CHBA’s Adaptiv Home Renovation program for accessibility and aging-in-place work. Urban Structures is a member of the Chatham-Kent Home Builders’ Association (CKHBA), part of the Ontario and Canadian Home Builders’ Associations, and a RenoMark renovator.